Uganda’s dream to achieve its first commercial oil production and crude exports has been delayed yet again, extending the country’s wait to more than two decades since commercial…
Alex Kimani is a veteran finance writer, investor, engineer and researcher for Safehaven.com.
Uganda’s dream to achieve its first commercial oil production and crude exports has been delayed yet again, extending the country’s wait to more than two decades since commercial oil reserves were first discovered in the country in 2006.
Officials from the Uganda National Oil Company (UNOC) and the Petroleum Authority of Uganda (PAU) have announced that Uganda’s first oil production and exports have now been pushed back to before the end of June 2027, blaming the delay on international supply chain bottlenecks and disruptions linked to the war in Iran. According to the PAU, the Middle East conflict delayed key equipment and material deliveries such as parts for metering, electrical instrumentation and telecommunications systems required to finalize the production and evacuation infrastructure.
The delay will create a rather substantial hole in the country’s budget, with Uganda’s Finance Minister Henry Musasizi telling parliament in June that the Ush 84.39 trillion budget for FY 2026/2027 had projected petroleum revenues of Ush 1.44 trillion (~$380 million).
According to Ugandan officials, while construction work at the $5.6-billion East African Crude Oil Pipeline (EACOP) is more than 90% complete, critical supporting facilities such as pump stations three and four and the pipeline’s electrical, instrumentation, telecommunications and security systems are still incomplete, requiring coordinated testing and commissioning across the EACOP, Tilenga, Kingfisher and Tanga projects. Lawmakers put the Tilenga Project at 78% complete and the Kingfisher development at 90% in October; however, the Central Processing Facilities (CPFs) required to treat and stabilize the raw crude are still undergoing final installation and pre-commissioning.
Uganda is projected to achieve a combined peak output of about 230,000 barrels of oil per day across TotalEnergies’ (NYSE:TTE) Tilenga project and…