FAA outage puts decades of delayed air traffic upgrades under renewed scrutiny as watchdog warnings surface

Publicado por Hindustan Times · India hace 59 min
Federal audits had repeatedly flagged aging systems, contract delays and oversight failures years before last week’s nationwide ground stop. Ryan Murphy/Getty Images/AFP (Getty Images via AFP)
Federal audits had repeatedly flagged aging systems, contract delays and oversight failures years before last week’s nationwide ground stop. Ryan Murphy/Getty Images/AFP (Getty Images via AFP) · Hindustan Times

Resumen detallado

Federal audits had repeatedly flagged aging systems, contract delays and oversight failures years before last week’s nationwide ground stop.

The five-hour nationwide ground stop that disrupted thousands of flights across the United States has renewed scrutiny of years of federal warnings about the country’s aging air traffic control infrastructure. Government watchdogs have previously pointed to repeated delays, oversight failures and costly contract extensions long before last week’s outage.

Transportation Secretary Sean Duffy said investigators are examining whether a decades-old router, which was supposed to be replaced in 2006, played a role in the November 13 disruption that halted departures nationwide.

Officials have not yet identified the final cause, but Duffy said the problems “go back decades” as the Federal Aviation Administration (FAA) continues to rely on outdated technology.

Also read: United Airlines hit by widespread system outage days after FAA ground stop disrupted US air travel

Fresh attention has focused on defence contractor L3Harris Technologies, which has managed much of the FAA’s telecommunications infrastructure for more than two decades.

According to a 2024 report by the Department of Transportation’s Office of Inspector General, the FAA improperly authorised 10 non-competitive contract extensions after the original 2002 agreement. The extensions added 57 months to the programme and increased spending by about $1.5 billion, CBS reported.

The inspector general warned that repeatedly extending contracts without competition risked increased costs and reduced service quality. The audit said the FAA may have relied on the extensions for “convenience and administrative ease” instead of pursuing competitive procurement.

Government concerns stretch back much further. Audits issued in 2006 and 2008 warned that L3Harris Technologies was falling behind schedule and continued to experience reliability issues affecting air traffic control operations.

In 2009, a telecommunications outage delayed more than 800 flights. The DOT IG investigated the incident and concluded that the FAA had not…

Inicio del artículo, extracto de Hindustan Times. Para leer el resto, abra el artículo en el sitio del medio.

Leer el artículo completo en Hindustan Times Inicie sesión para guardar

MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (www.hindustantimes.com)

También te puede interesar