Another heavily curtailed solar farm seeks approval to add a big battery

Publicado por RenewEconomy · Australia hace 15 h
Goonumbla solar farm
Goonumbla solar farm · RenewEconomy

Resumen detallado

Another solar farm that suffers from heavy curtailment - both from network constraints and low prices - is seeking planning and environmental approvals to ...

Another solar farm that suffers from heavy curtailment – both from network constraints and low prices – is seeking planning and environmental approvals to add a big battery to the project to allow it to store power for when it is needed more.

There are now virtually no solar farms being built in Australia without a big battery, and the number of existing solar farms choosing to add batteries to their already operating projects is also increasing.

The latest is the Goonumbla solar farm, near Parkes in western NSW, and just up the road from the first true solar-battery hybrid to operate in Australia’s National Electricity Market, the newly-completed Quorn Park facility.

FRV is seeking to add a 140 MW battery (its application does not yet specify the amount of storage) to the 83.5 MW (dc) Goonumbla solar farm that was completed in 2020.

It is in the process of preparing a planning application with the state government and has sought environmental approval from the federal government under the auspices of the EPBC Act. It has met with the local council and mayor, and has also started engaging with the local community and First Nation peoples about its plans.

The proposal from FRV for Goonumbla does not lay out the reasons for the battery addition, but the facility is one of many in the area that suffers from curtailment, both voluntary as a result of low or negative wholesale prices, or enforced as a result of network limitations.

According to analysts at Rystad Energy, the level of curtailment in the past year at Goonumbla has been 34 per cent, most of it due to network limitations.

Meanwhile, work is soon to commence on a 102 MW, 408 MWh battery that will be added to the 102 MW Glenrowan solar farm in Victoria, which was only completed in 2024 but is also suffering heavy curtailment.

To support independent media, and help combat the spread of deliberate misinformation and disinformation about the energy transition, you can click here to make a one off donation or become a…

Inicio del artículo, extracto de RenewEconomy. Para leer el resto, abra el artículo en el sitio del medio.

Leer el artículo completo en RenewEconomy Inicie sesión para guardar

MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (reneweconomy.com.au)

También te puede interesar