US Data Center Boom Faces a New Political Reality

Resumen detallado
Starting in January, Democratic governors will lead US states that together hold 77% of the 300 gigawatts (GW) of data center capacity announced for 2027-2030, including the five…
Rystad Energy is an independent energy consulting services and business intelligence provider offering global databases, strategic advisory and research products for energy companies and suppliers,…
Starting in January, Democratic governors will lead US states that together hold 77% of the 300 gigawatts (GW) of data center capacity announced for 2027-2030, including the five largest markets: Texas, Virginia, Pennsylvania, Ohio and Georgia. Most of the winning candidates campaigned on making data centers pay their grid costs, rather than on stopping them, so the midterms are likely to change the terms of growth more than its pace.
Our risked forecast expects 121 GW to be added in 2027-2030, including about 49 GW of the 191 GW planned for 2029-30. Texas had implemented a permit pause but lifted it on 17 November at the behest of outgoing Governor Greg Abbott. Governor-elect Gina Hinojosa has pledged to implement a new one which, if it lasts until new rules take effect in September 2027, will delay about 3 GW of capacity. If the pauses are sustained for another year, over 10 GW is pushed back, and installed capacity at the end of 2029 would be about 170 GW instead of 177 GW. We expect most of the delayed capacity to be online by the end of 2030.
Pauses delay little, and mostly in Texas. Most moratoria across the US stop or delay only projects that are still awaiting approval. About half of the capacity planned for 2027-28 is already under construction or roofed. Of the planned capacity we expect, 16% still needs approval and is thus exposed to political changes. Slow construction already pushes nearly a third of the capacity we expect for 2027-28 past its planned year, far more than the pauses delay.
Texas's permit pause has ended, but a new one may follow. Texas's environmental regulator, TCEQ, stopped issuing data center permits in September but resumed its reviews on 17 November, two weeks after Abbott lost his bid for a fourth term.
The window requires developers to…