PJM Interconnection, the biggest grid operator in the United States, has proposed to the Federal Energy Regulatory Commission to streamline the processes related to new power…
America’s Biggest Grid Operator Races to Keep Up With Data Center Boom
PJM Interconnection, the biggest grid operator in the United States, has proposed to the Federal Energy Regulatory Commission to streamline the processes related to new power generation capacity commissioning and large consumer connections in a bid to speed it all up.
PJM, which operates in 13 states, has been struggling to cope with the sharp demand rise resulting from the proliferation of data centers, which has created a supply shortfall of some 6.8 GW, according to a Reuters report. Unless PJM secures generation capacity to cover that, the grid in those 13 states could become less reliable.
The shortfall was revealed in PJM’s June 2028/2029 electricity procurement auction, organized earlier this year. The amount of capacity is what PJM needs to find before that year to make sure there is enough generation during demand spike periods.
“Neither generation nor transmission is coming online quickly enough to keep pace with new demand growth driven mainly by large loads like data centers,” company spokesman Jeff Shields said. "The factor that PJM planning can influence is how quickly these new resources are studied for reliability."
Last month, PJM had to issue a Maximum Generation Alert as a warm front moving across its area of operation met planned generation capacity maintenance, leading to a supply squeeze as some 62 GW in capacity were offline for maintenance. The unfavorable combination of circumstances prompted electricity prices to shoot up to over $1,000 per megawatt-hour.
To tackle these challenges, PJM has proposed to FERC to reduce the time now required for the study of connecting new demand sources to the grid, from two years to 12 months. By streamlining its processes, the grid operator would also be able to identify the places for the most urgent grid upgrades related to the connection of new data centers.
The materials provided on this Web site are for informational and educational…
Nothi…
Inicio del artículo, extracto de OilPrice.com. Para leer el resto, abra el artículo en el sitio del medio.
MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (oilprice.com)