Forrestania puts finishing touches on December WA gold restart
Resumen detallado
Forrestania Resources has secured key contracts for its Edna May gold mine and opened a Kalgoorlie hub, targeting a December gold pour as it gears up for production.
Forrestania Resources has ticked a string of key operational boxes as it barrels towards a December first gold pour at its Edna May Gold mine in Western Australia, locking in critical supply and services contracts and establishing a new operational hub in the heart of the Goldfields.
In a significant step towards wet commissioning, Forrestania has executed a long-term supply agreement with Australian Gold Reagents for sodium cyanide, a critical reagent required for gold recovery operations.
At the same time, the company has awarded the ore loading and crusher feed contract to Campbell Gold Haulage. The deal supports ore handling requirements at both its 2.9-million-tonne per annum (Mtpa) Edna May and 3.2Mtpa Lake Johnston hubs. It also delivers operational efficiencies, as Campbell already holds the road train contract for delivering ore to both of Forrestania’s run-of-mine (ROM) pads. Campbell has already begun mobilising equipment and personnel to site.
To support its growing operational footprint, Forrestania has now planted a flag in Kalgoorlie, establishing a dedicated office that will serve as its goldfields operations hub. The company says the new facility showcases its commitment to building a long-term operating presence in WA’s premier gold district. In a savvy operational move, the new office will be shared with Forrestania’s mining contractor MEGA Resources.
The office will be led by newly appointed “general manager mining”, Darren Gaby, an experienced hand with more than three decades of operational and project development experience in the WA goldfields. Notably, Gaby previously led the development of Beacon Minerals’ Jaurdi Gold project from construction through to production.
Forrestania says it has 60,000 tonnes of ore on the ROM pad at Edna May, with first processing fast approaching. Its second strategic hub at Lake Johnston, slated to be operational in early 2027, is also well-stocked, with ore inventories exceeding 180,000 tonnes and the ROM…
The…
Forr…
Inicio del artículo, extracto de The Age. Para leer el resto, abra el artículo en el sitio del medio.
MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (www.theage.com.au)




