Seven Down, Three To Go: America's Microreactors Keep Going Critical

Resumen detallado
Seven Down, Three To Go: America's Microreactors Keep Going Critical Of the four nuclear executive orders President Trump signed in May 2025, the most ambitious target was…
Of the four nuclear executive orders President Trump signed in May 2025, the most ambitious target was arguably within EO 14301: approve at least three test reactors outside the national labs, "with the goal of achieving criticality in each of the three reactors by July 4, 2026."
While most people referred to the July goal as a fantasy, the industry not only exceeded the goal with four reactors achieving criticality by the date, but 2026 now stands at a total of seven new microreactor designs splitting uranium atoms within their cores.
DOE picked 11 projects from 10 companies for its Reactor Pilot Program on Aug. 12, 2025. The companies signed up to pay for everything themselves to test under DOE authorization instead of an NRC license.
Less than ten months later, Antares Nuclear's Mark-0 went critical at Idaho National Laboratory (INL) on June 4. Energy Secretary Chris Wright called it the first new privately developed non-light-water reactor to reach criticality in America in more than four decades.
"Nine months ago, this was an empty site," Valar Atomics CEO Isaiah Taylor said after Ward 250 went critical in Utah on June 18.
Deployable Energy, which DOE only picked in April for the pilot program's successor, the Nuclear Energy Launch Pad, took its Unity reactor critical on June 30. Aalo Atomics followed at 12:19 a.m. on July 4, about ten months after breaking ground.
As we noted at the time, the goal was met with days to spare. Oklo's Groves-1 isotope test reactor in Lockhart, Texas, made it five on Aug. 5, less than a year after construction started.
The DOE's pilot programs accounted for five, but the other two came out of the National Criticality Experiments Research Center (NCERC) in Nevada.
One of them actually beat everybody. Los Alamos National Laboratory (LANL) took its ZiaCore microreactor experiment critical over the course of four weeks in April and May, ahead of Antares, then didn't announce it until July 30.
Inicio del artículo, extracto de ZeroHedge. Para leer el resto, abra el artículo en el sitio del medio.
MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (www.zerohedge.com)



