Over-size, over-mass and under pressure: Logistical barriers could delay wind projects by up to three years

Publicado por RenewEconomy · Australia hace 15 h
A stuck turbine tower in Queensland. Image source: Facebook, City Watch – Keeping Ipswich Safe!
A stuck turbine tower in Queensland. Image source: Facebook, City Watch – Keeping Ipswich Safe! · RenewEconomy

Resumen detallado

New report warns Australia's straggling wind project pipeline could be delayed even further by inadequate port facilities and limits on major road corridors.

Australia could miss its renewable energy targets if it does not address barriers to building wind farms, including inadequate port infrastructure and limits on major road corridors.

A failure to act could delay some wind projects by almost three years, a study has found, and contribute to higher electricity prices.

Infrastructure Australia issued the warnings in an analysis of the nation’s onshore wind pipeline on Tuesday, which called for urgent regulatory changes and freight upgrades.

The findings come weeks after Australia set a renewable energy record, with solar, wind and batteries meeting 80.4 per cent of demand in the National Electricity Market during a half-hour period.

The authority’s report, Enabling Infrastructure for the Energy Transition, analysed 56 onshore wind projects due to start construction by 2030 with a combined generation capacity of about 30 gigawatts.

It found the projects would require more than 4500 turbines and more than 62,000 oversize, over-mass vehicle movements, putting strain on Australian ports and road corridors.

In 2027 alone, more than 18,500 oversize loads were expected on Australian roads.

The scale of Australia’s wind projects had the potential to overwhelm existing roads, bridges and ports without greater planning, Infrastructure Australia chief executive Adam Copp said.

“A wind turbine blade is anywhere from 82 to 102 metres long… it can be double the length of a Boeing 737 or as long as the Statue of Liberty,” he told AAP.

Inicio del artículo, extracto de RenewEconomy. Para leer el resto, abra el artículo en el sitio del medio.

Leer el artículo completo en RenewEconomy Inicie sesión para guardar

MarketNews muestra el titular y el resumen publicados por el medio. El artículo completo se lee en el sitio del editor. (reneweconomy.com.au)

También te puede interesar