Calibration flight planned for Long Thanh airport's second runway in early December

Resumen detallado
Under an earlier-announced plan, Long Thanh Airport would begin operations in three phases starting from 00:00 on December 24, 2026. However, the Airports Co...
A calibration flight for the second runway at Long Thanh International Airport is scheduled to be carried out in early December 2026, according to the Airports Corporation of Vietnam (ACV).
For the second runway (Runway 3), ACV will continue completing the necessary procedures following the calibration flight and publish operational information through the aeronautical information notification system, paving the way for the runway to enter service.
Under an earlier-announced plan, Long Thanh Airport would begin operations in three phases starting from 00:00 on December 24, 2026.
However, at a meeting with Standing Deputy Prime Minister Pham Gia Tuc on November 25, the Airports Corporation of Vietnam (ACV) - the developer of the airport - has proposed extending the deadline for completing the first phase of Long Thanh International Airport to 2027 or 2028, because some parts of the project will remain unfinished this year.
Speaking at the meeting, Standing Deputy Prime Minister Pham Gia Tuc stressed that safety and convenience for users are top priorities for an international airport. The airport can open only when it meets all requirements and can operate safely.
In late March 2025, the Prime Minister approved an adjustment to Phase 1 of the Long Thanh Airport project, including the construction of the second runway.
The second runway has been developed to the same specifications as the first runway, with a length of 4 km and a width of 75 m.