Japan’s Nuclear Revival Hits a Snag as TEPCO Delays Reactor Restart

Resumen detallado
Tokyo Electric Power Company (TEPCO) will delay the restart of a second reactor at its Kashiwazaki-Kariwa nuclear power plant in Japan, the world’s largest in terms of nameplate…
What I Cover Tsvetana Paraskova is an energy and commodities journalist who has contributed to Oilprice.com for nearly a decade, covering global energy markets, commodities,…
Tokyo Electric Power Company (TEPCO) will delay the restart of a second reactor at its Kashiwazaki-Kariwa nuclear power plant in Japan, the world’s largest in terms of nameplate capacity, after identifying a problem with the construction at the facility.
TEPCO, which also operated the nuclear power plant in Fukushima prior to the 2011 disaster, has planned for years to restart the Kashiwazaki-Kariwa plant in the Niigata prefecture.
Finally, the company restarted earlier this year Unit 6, the first reactor at the nuclear power plant with a nameplate capacity of nearly 8 gigawatts (GW), returning to nuclear power generation after nearly 15 years following the Fukushima disaster.
Before the Fukushima meltdown in 2011, nuclear energy accounted for about 30% of Japan’s electricity mix. The disaster prompted the closure of all reactors for safety checks. Since 2015, Japan has restarted 15 reactors out of 33, while 7 are in the process of restart approval.
TEPCO, specifically, planned to restart a second reactor at the Kashiwazaki-Kariwa plant, Unit 7, by August 2029.
However, the company identified in September a problem with the strength of the concrete construction housing the reactor. This means TEPCO must revise the construction and restart schedule for Unit 7 to comply with the counter-terrorism requirements of Japan’s nuclear safety watchdog, which mandate strong enough facility to withstand a deliberate plane crash.
Takeyuki Inagaki, superindendent of the Kashiwazaki-Kariwa nuclear power station, told a media briefing on Thursday that it was too early to provide a revised timeline. However, the executive noted that the contractor which would build the structure to house the reactor had said the August 2029 restart date could slip by more than one year.
“It will take time to determine the cause,”…