Australia's largest proposed vegetation-fuelled power plant rejected again
Résumé détaillé
A court has dismissed an appeal brought by the company behind what would have been Australia's largest modern biomass generator, in the NSW Hunter Valley.
A court has upheld the ruling to refuse a biomass power generator near Singleton, NSW.
Environmentalists say it's a huge win, but the company behind it isn't backing down.
A partnership with a data centre proposed for adjoining land is now in doubt
A court has knocked back an appeal brought by the company planning to build Australia's largest modern biomass generator in the NSW Hunter Valley.
Verdant Earth Technologies has been working to transform the former coal-fired Redbank Power Station near Singleton into a bioenergy hub since it took over the site in 2018.
The plan, initially put to the NSW Independent Planning Commission (IPC), was for it to be fuelled by invasive native species (INS) plaguing farmers in western NSW, as well as purpose-grown plants.
The proposal was for 700,000 tonnes of dry material to be burned each year to fuel the 151-megawatt proposal, which the company said could power approximately 200,000 homes.
The NSW Planning Department was told the capital investment would surpass $70 million, with the project creating 330 jobs during construction and 60 operational positions.
But the IPC last year rejected the proposal, noting the "potential benefits" for energy security and reliability, as well as employment opportunities, but ultimately ruling that the environmental impact was too great.