Making Danantara's waste-to-energy plan work

详细摘要
Indonesia has finally solved the financing puzzle holding back its WtE ambitions, but the program’s survival now hinges on three things money cannot buy: dry feedstock, fiscal transparency and real technology transfer.
Your browser is out of date, and may not be compatible with our website. A list of the most popular web browsers can be found below. Just click on the icons to get to the download page.
Indonesia has finally solved the financing puzzle holding back its WtE ambitions, but the program’s survival now hinges on three things money cannot buy: dry feedstock, fiscal transparency and real technology transfer.
residential Regulation (Perpres) No. 109/2025 has resolved the financing bottleneck that stalled Indonesia’s waste-to-energy (WtE) ambitions for more than a decade. Yet the program will only succeed if it also overcomes three challenges that capital alone cannot solve: feedstock quality, the long-term fiscal burden and genuine technology transfer.
In July, construction began on a WtE facility in the Balinese capital designed to process up to 1,500 tonnes of municipal waste daily from Greater Denpasar, the first project under a new initiative from state asset fund Danantara. Groundbreakings in Jakarta’s buffer cities Bekasi and Bogor, both in West Java, followed respectively in August and September.
At each ceremony, the project company executed a power purchase agreement (PPA) with state electricity firm PLN. Eight additional consortia received conditional awards in July and are scheduled to complete feasibility studies by mid-November.
Indonesia has trodden this path before. In 2016, a Perpres aimed at fast-tracking WtE plants across seven cities was struck down by the Supreme Court within months. A 2018 replacement expanded the mandate to 12 cities, yet only two facilities, the Benowo in Surabaya, East Java, and the Putri Cempo in Surakarta, Central Java, ever entered commercial operation.
In Jakarta, the Sunter project broke ground in 2018 alongside Finland’s Fortum, only for the energy company to withdraw after failing to secure a financing guarantee from the central government, according to municipal officials.
Even the Legok Nangka, a Japanese-led project in West Java…
W…