The new €2 billion-plus Greater Dublin Drainage (GDD) project will be delivered by the end of 2031, 20 years after the scheme was first proposed. Taoiseach Micheál Martin turned…
The new €2 billion-plus Greater Dublin Drainage (GDD) project will be delivered by the end of 2031, 20 years after the scheme was first proposed.
Taoiseach Micheál Martin turned the sod on Monday for the new regional facility which will be based on a 30-hectare site at Clonshaugh in north Dublin.
Once completed the scheme will ensure up to 185,000 new homes in north Dublin, south Meath and east Kildare will have access to wastewater services and will support a population of 500,000.
The project will provide a second substantial wastewater facility in the Greater Dublin Area along with the existing plant at Ringsend.
There will also be a 14km orbital sewer connecting the Dublin suburbs of Blanchardstown and Clonshaugh, as well as a pumping station at Abbotstown.
An 11km marine outfall pipe will discharge treated water into the Irish Sea, about 6km from shore. A biosolids and sludge hub will also be built at Kilshane.
Uisce Éireann has given a provisional range for the final budget at between €1.9 billion and €2.3 billion when the main works are completed in 2031.
Minister for Housing James Browne, Minister for Public Expenditure Jack Chambers and Uisce Éireann chief executive Niall Gleeson also attended Monday’s launch.
Martin said the scheme would be largely “invisible” but would be “fundamental to supporting economic development and enabling new housing”.