Metair warns it cannot afford an indefinite Durban port crisis

详细摘要
Major vessel delays threaten to disrupt import-dependent businesses as festive season approaches.
Automotive component manufacturer Metair says there is a limit to how much it can absorb in additional costs arising from delays of up to 20 days for vessels awaiting unloading at Durban Gateway Terminal (DGT), which operates the country’s largest container facility, Durban Container Terminal Pier 2.
Metair CEO Paul O’Flaherty tells Moneyweb the delays started in July but have since deteriorated to the point where ships are spending between 14 and 20 days at anchorage.
Read: Metair may invoke ‘force majeure’ over Durban Gateway Terminal crisis
The group’s shares plunged more than 35% on Friday after it warned that it may be forced to invoke force majeure in its supply contracts as port delays reach “crisis proportions”.
“There’s no end [to the crisis] in sight, in my view,” says O’Flaherty.
“I have customer contracts and I cannot stop their production lines, so I have to bring in air freight and then work serious overtime, working stop-start, to service the customer. There’s a very real cost to that.
“There can never be an open cheque book. I can weather a certain storm, but I cannot weather it endlessly.”
This contributed to Durban ranking dead last in the World Bank and S&P Global’s 2024 Container Port Performance Index. However, the port recorded the biggest improvement among the ports assessed in 2025.
The latest crisis will do little to help its efforts to move away from the bottom end of the rankings.