First production of magnesium metal from waste fly ash is closing in, targeted for the end of 2026. ... Read More The post The final countdown: Latrobe Magnesium closes in on…
LMG is closing in on the first production of magnesium metal. Pic: Getty Images
Special Report: Latrobe Magnesium has completed installing the final stage of its Victorian Demonstration Plant and begun heating the reduction furnace, putting it within reach of producing first magnesium metal before the end of 2026.
The latest progress marks a significant advance for the company’s Phase 1B project, which is designed to convert magnesium oxide into magnesium metal crowns containing more than 98% magnesium.
All equipment is installed while commissioning has reached 78%, up from 50% at the end of October and just 35% in mid-October.
The acceleration brings Latrobe Magnesium (ASX:LMG) closer to a milestone that has been years in the making: demonstrating its ability to produce magnesium metal using a process developed to recover valuable materials from industrial waste.
The project remains within its original $6.1 million budget with all key operational positions filled and the reagents required for the first four-week production campaign already on site.
The start of furnace heating follows completion of the final furnace seal and successful ignition testing.
Commissioning of the reagent milling and briquetting systems has also been completed with the first batch of magnesium oxide feed briquettes produced and ready for introduction into the retort.
These briquettes will be heated in the reduction furnace, where magnesium oxide is converted into magnesium metal.