The US Army has asked contractors to register interest in building 17 precast concrete bunkers at military sites in Saudi Arabia, Israel and Lebanon to protect US and coalition…
The US Army has asked contractors to register interest in building 17 precast concrete bunkers at military sites in Saudi Arabia, Israel and Lebanon to protect US and coalition personnel from indirect fire.
The notice was issued on 13 November by the US Army Contracting Command for US Army Central. Area Support Group-Jordan's Directorate of Public Works is acting as the servicing agency for the requirement.
Israel accounts for 10 of the bunkers, all at one site. Five are planned across two sites in Saudi Arabia, and two across two sites in Lebanon. The notice says the names and coordinates of the bases will be given only to verified, eligible bidders once a formal solicitation is released.
The notice cites elevated regional force protection conditions. It says there is an urgent, high-priority requirement to replace non-standard shelters, including converted shipping containers, with standardised bunkers.
Each bunker will be made of three sections of precast, reinforced concrete C-channel culvert. The contractor will also supply and install reinforced concrete Alaska barriers. These are 3 metres high and weigh about 6.1 tonnes each, and will stand at entry and exit points. The scope also covers sandbag revetments on the roofs and walls, steel blast doors, land surveys and the demolition of existing non-standard bunkers and T-walls.
Contractors must submit designs at the 60%, 90% and 100% stages, each signed by a licensed professional engineer. Manufacturers' concrete test reports are required before delivery.
The army plans to award a firm-fixed-price contract. Each country task order will have a 45-day performance period. The first 15 days are for base access, security vetting, surveys and submittal reviews. The notice to proceed will be issued no later than day 15, and construction, assembly and inspection will follow between days 16 and 45.
Because of what the notice calls extreme operational urgency, bidders are expected to get only three days to respond to the formal…
Opening of the article, excerpted from MEED. To read the rest, open the article on the publisher's site.