Senate tries again to force release of NRMA’s hidden “Grit in the Gears” report on failed EV charging plan

Publié par The Driven · Australie il y a 33 min
The new off-grid fast charger at Edrlunda. Photo courtesy of NRMA.
The new off-grid fast charger at Edrlunda. Photo courtesy of NRMA. · The Driven

Résumé détaillé

Senate asks again for release of NRMA report into the shortfall of its proposed national EV charging network that has been kept hidden for commercial reasons. The post Senate…

The Senate has passed a third resolution seeking the release of the “Grit in the Gears” report written by the NRMA motoring group, which is believed to have identified the problems that prevented it from delivering the proposed national network of EV chargers as planned.

The Senate first called for the release of the Grit in the Gears report in September, then set an October deadline, and this week put a new deadline of November 25 (Wednesday). The motion was put forward by the federal Coalition approved in a vote 35-20 with the support of the Greens and independents.

The request has previously been refused by energy and climate minister Chris Bowen on the basis that its content is commercially sensitive and claiming public immunity. There is no evidence that the report has been released after the latest request.

As The Driven reported last month, The Grit in the Gears report – subtitled “Lessons from the frontline of building a national EV network” – delves into how NRMA came up short in the $78 million plan to roll out 117 EV charging stations across the nation. Around 62 have so far been completed, according to an NRMA spokesperson.

The 21-page report has actually been published on the Department of Climate Change, Energy and the Environment website, but is totally redacted, bar one single line that identifies the average cost of the charging installations – $350,000.

The NRMA won the contract to roll out the national charging network in April, 2023, with $39 million in funding from the Australian Renewable Energy Agency, and agreeing to match that sum with its own money. The plan was to build a network around Australia, to ensure there was a charger every 150 km along major routes.

But the program ran into significant issues, particularly in regional and off-grid areas. According to a report published in the AFR in March only 45 of the EV charging stations had been installed, little more than one third of the target.

One report that was published on ARENA’s website in…

Début de l'article, extrait de The Driven. Pour lire la suite, ouvrez l'article chez le média.

Lire l'article complet sur The Driven Connectez-vous pour sauvegarder

MarketNews présente le titre et le résumé publiés par le média. L'article complet se lit sur le site de l'éditeur. (thedriven.io)

À lire aussi