As fuel prices hit record highs, calls grow for South Africa to build state-owned refineries. Legal experts explain the complex regulatory approvals, risk…

Petrol and diesel has crossed R30 a litre in Gauteng, and the conversation has turned, understandably, to a big idea. If we cannot control the oil price, why not refine more of our own fuel? Calls for the government to build or own refineries are growing louder.

As lawyers who spend our working lives on the approvals, contracts, and disputes behind major projects, we think the idea deserves to be taken seriously. That means reading the fine print before anyone pours a foundation.

A refinery is not just a very large construction project. It is a small city of technology, equipment, contractors, interfaces, and commissioning, all of which must work together at the end. The hard work starts long before construction. Who carries the design risk? Who manages the interfaces? How do we deal with imported equipment and currency swings? What happens when things are late, and who is accountable for making the whole machine work?

These are not legal technicalities. A contract cannot perform miracles. If you push risk onto parties that cannot price, manage, or absorb it, you have not removed the risk. You have simply put it somewhere it is more likely to become a dispute.

Before a single brick is laid, a refinery also needs a stack of approvals. Three environmental licences sit at the top of the list: an environmental authorisation under the National Environmental Management Act, an atmospheric emission licence for the furnaces, boilers, flares, and stacks, and a water use licence – and that’s just the basics. Depending on how the plant handles its hazardous waste, a waste management licence may matter just as much. Then come biodiversity, coastal, heritage, land-use, hazardous substance, municipal, building and fire approvals.

On paper, the regulated timelines run to about a year. In practice, with appeals, objections, and the involvement of interested and affected parties, two to three years is common.

Then there is the question the Minister has raised: why do so many of these…

Usua…

Début de l'article, extrait de Mail & Guardian. Pour lire la suite, ouvrez l'article chez le média.

Lire l'article complet sur Mail & Guardian Connectez-vous pour sauvegarder

MarketNews présente le titre et le résumé publiés par le média. L'article complet se lit sur le site de l'éditeur. (mg.co.za)

À lire aussi