Norway Pauses Data Center Grid Reservations As Requests Top Peak Demand

Publié par ZeroHedge · États-Unis il y a 3 h
Norway Pauses Data Center Grid Reservations As Requests Top Peak Demand
ZeroHedge

Résumé détaillé

Norway Pauses Data Center Grid Reservations As Requests Top Peak Demand Authored by Rystad Energy via OilPrice.com,Statnett froze new data center grid reservations on Nov. 9, and…

Norway's transmission system operator Statnett paused new grid reservations for data centers on November 9, the same day the government announced a licensing scheme that will keep out new crypto mining. The grid reservation halt will last until at least August 2027, when a new system is set to come into effect. Both moves come as data center demand threatens Norway's long-standing power surplus.

Data centers have asked for about 34 gigawatts (GW) of grid capacity in Norway, well above national peak demand of about 25 GW. Only 0.8 GW is connected today. Another 4.2 GW holds reserved capacity, 10.8 GW is in the queue, and 18 GW is still at the inquiry stage.

Statnett has stopped granting new reservations and approving facility functionality under the Regulation on System Responsibility (fos) § 14 rule while it sets functional requirements for data centers. These will cover when facilities must stay connected during disturbances, how quickly their load may change and how to limit grid fluctuations. Projects with reserved capacity keep their place but still need approval before connecting, and existing connections are not affected.

About half of the queue has asked for power by the end of 2028. With no new reservations until August 2027 at the earliest, and grid build-out still to follow, those dates look out of reach for established operators and newcomers alike.

Norway is not alone. Grid operators across Europe are replacing first-come, first-served queues with rules that favor projects able to show progress. Great Britain, Germany and Denmark have all tightened their connection rules since 2025.

Satellite images show how far projects due in 2027-28 have to go. In the UK, almost two-thirds of the 2027-28 capacity has no building under way. In the Nordics, it is just over a third. In Norway, about half of the 1.5 GW due in 2027-28 shows new construction, but a single project accounts for most of it.

Norway has six operating crypto data centers with about 0.2 GW combined.

Hydr…

Début de l'article, extrait de ZeroHedge. Pour lire la suite, ouvrez l'article chez le média.

Lire l'article complet sur ZeroHedge Connectez-vous pour sauvegarder

MarketNews présente le titre et le résumé publiés par le média. L'article complet se lit sur le site de l'éditeur. (www.zerohedge.com)

À lire aussi