Tajikistan plans to commission unit 3 of Rogun HPP in Sept 2027, three more by 2031 - Energy Ministry

Published by Interfax · Russia 17 h ago

Detailed summary

DUSHANBE. Nov 12 (Interfax) - Tajikistan plans to commission the third unit of the Rogun hydropower plant (HPP) in September 2027 and the remaining units by 2031, Tajik Energy and…

DUSHANBE. Nov 12 (Interfax) - Tajikistan plans to commission the third unit of the Rogun hydropower plant (HPP) in September 2027 and the remaining units by 2031, Tajik Energy and Water Resources Minister Daler Juma said.

"Currently, construction work at the plant is almost 70% complete," Juma was quoted as saying by the Energy Ministry's press center at a meeting of the lower house of the Tajik parliament on Thursday.

The design capacity of the Rogun HPP is 3,780 MW. The implementation of the project is of strategic importance for achieving energy independence and ensuring the sustainable development of the country's economy, Juma said.

It is noted that 37 state investment projects worth a total of 30 billion somoni have been implemented in Tajikistan's energy sector in total over the years of independence. Another 20 projects worth 23 billion somoni are currently being implemented. Thanks to the commissioning of more than 2,300 MW of new generating capacity, the installed capacity of the country's energy system has exceeded 6,700 MW. Electricity generation has increased from 17.4 billion kWh in 1991 to 24 billion kWh in 2025.

Tajikistan continues to modernize its existing hydropower plants. As a result of the reconstruction of three units at the Nurek HPP, its capacity increased by 120 MW. After all work is completed in 2031, the plant's capacity will be brought to 3,375 MW. The capacities of the Kayrakkum, Sarband and Varzob HPP-1 have also been increased.

Tajikistan also intends to accelerate the development of renewable energy. Two solar power plants with a total capacity of 500 MW are under construction in the Asht and Jayhun districts. The construction of additional photovoltaic capacity of 1,000 MW will be achieved by the end of 2027.

As part of the development of regional energy infrastructure, the CASA-1000 project continues to be implemented, along with the construction of the South-North power transmission line and work to connect the northern part of the…

Elec…

Opening of the article, excerpted from Interfax. To read the rest, open the article on the publisher's site.

Read the full article on Interfax Sign in to save

MarketNews shows the headline and summary published by the outlet. The full article is on the publisher's website. (interfax.com)

Also worth reading