Puerto Rico Supreme Court cancels key power contract as many wonder what’s next

详细摘要
The 5-4 ruling made public Wednesday plunges the island into further uncertainty as many wonder who will take over from Luma while power outages persist across the US territory.
SAN JUAN, Puerto Rico (AP) — Puerto Rico’s Supreme Court has narrowly ruled in favor of canceling the government’s contract with Luma Energy following a contentious legal fight with the private power company.
The 5-4 ruling made public Wednesday plunges the island into further uncertainty as many wonder who will take over from Luma while power outages persist across the US territory and crews continue to repair the grid razed by Hurricane Maria in 2017.
Puerto Rico’s government had awarded a multimillion-dollar contract to Luma, which took over the transmission and distribution of power on the island in June 2021. It inherited infrastructure that was crumbling after decades of neglect and mismanagement under Puerto Rico’s Electric Power Authority.
The company said in a statement Wednesday that it disagrees with the court’s decision but will respect the judicial process and is “carefully evaluating all available legal alternatives.”
“We remain concerned about the potential impact of this decision on ongoing efforts to strengthen and modernize Puerto Rico’s electric grid,” Luma said. “This matter goes beyond a contractual dispute. It has significant implications for the provision of an essential electric service, public safety, and Puerto Rico’s energy future.”
Luma is a consortium made up of Calgary, Alberta-based Atco and Quanta Services Inc. of Houston.
Puerto Rico’s government sued Luma nearly a year ago, following up on a campaign promise made by Governor Jenniffer González to cancel the contract.
In December 2025, González said Luma had nearly $11 billion in federal funds at its disposal to rebuild the grid, but that it has only been able to recover some $550 million in reimbursements from the US Federal Emergency Management Agency.
When the lawsuit was filed, she said, “Despite the operator’s expectations and representations, the electrical system has not improved with the speed, consistency or effectiveness that Puerto Rico deserves and that LUMA promised and lied to…
文章开头,摘自The Boston Globe。如需阅读全文,请前往媒体网站。
MarketNews 仅展示媒体发布的标题和摘要,全文请在出版方网站阅读。 (www.bostonglobe.com)